b40.1850.track1.2deg.004


Contents:


Run Specifications


===================
General Information
===================

   Purpose of Run: validation run for jaguarpf

   Scientific Lead: Jim Hurrell

   Software Engineering Lead: Mariana Vertenstein, Jon Wolfe

   Assigned to: Diane Feddema
 
   Date: 2009-12-30

   Run Length:  200 years

 
=========================
Case Creation Information
=========================

   CCSM tag:   ccsm4_0_beta38

   Case Name:  b40.1850.track1.2deg.004

   Machine:    jaguarpf

   Compset:    B_1850_TRACK1_CN
 
   Resolution: 1.9x2.5_gx1v6


=============================
Pre-Configuration Information
=============================


   RUN_TYPE = hybrid
   RUN_STARTDATE = 0001-01-01
   RUN_REFCASE = 1850_f19_g16_c091124
   RUN_REFDATE = 0001-01-01

   Note: the necessary restart files can be found in:
         /tmp/proj/ccsm/inputdata/ccsm4_init/1850_f19_g16_c091124


   env_conf.xml mods 
   _________________

   * none


   env_mach_pes.xml mods
   _____________________
      
  component       comp_pes    root_pe   tasks  x threads (stride)
  ---------        ------     -------   ------   ------   ------
  cpl = cpl        160         0        160    x 1       (1     )
  glc = sglc       64          0        64     x 1       (1     )
  lnd = clm        160         0        160    x 1       (1     )
  ice = cice       320         0        160    x 2       (1     )
  atm = cam        320         0        160    x 2       (1     )
  ocn = pop2       240         160      240    x 1       (1     )


==============================
Post-Configuration Information
==============================

   Buildconf
   _________

  * none

  Note:  before building, please make the following changes to env_mach_specific:

         from

  module switch pgi       pgi/9.0.2         # 9.0.2 tested for bfb on 2009-sep-25
  module switch xt-mpt    xt-mpt/3.2.0      # 3.2.0 is default on 2009-sep-25
  module switch xt-libsci xt-libsci/10.3.5  # 10.3.5 is default on 2009-sep-25

         to

  module switch pgi       pgi/9.0.4         # 9.0.4 is default on 2009-dec-30
  module switch xt-mpt    xt-mpt/3.5.0      # 3.5.0 is default on 2009-dec-30
  module switch xt-libsci xt-libsci/10.4.0  # 10.4.0 is default on 2009-dec-30
 

======================
SourceMods Information
======================

  * none


==========================
Performance/Cost Estimates
==========================

  * 18.8 years/day

 
====================
Special Instructions
====================

  * please make sure to run in /tmp/proj/ccsm/runs/ccsm4_0/
 

====================
Pre-Run Instructions
====================

  * Run create_production_test
 
  * Run debug smoke test

  * Add NCAR Software Levels info to checklist 


================
Run Instructions
================

  Run Length: 200 years

  Account key: NA

  Priority/Targeted queue:  NA

  Other:

================
Diagnostics Plan
================

  * [put diagnostics plan here]


======================
Additional Information
======================

  * [put any additional information here]


Return to Top


Run Checklist


Complete the following checklist prior to beginning the production run:



1.  Update status file: /web/web-data/cseg/ccsm4_0_runs/b40.1850.track1.2deg.004/status.txt  [assigned, setup in progress, running]

2.  Document NCAR software levels at beginning of run (use the spinfo command on bluefire)

2.  Complete the following table, as necessary, showing
    the component liaison's name and the date the setup
    was approved.
 

   Component         Liaison/                     Date Approved
                     Reviewer
   ================+==========================+==================

      atm             hannay                          Sun Jan 10 22:05:00 MT 

      cpl            [kauff,mvertens,tcraig,other]    ----

      ice             dbailey                         Mon Jan 04 09:05:00 MT 

      lnd             erik,slevis                     Tue Jan 12 14:02:19 MT 

      ocn             njn01                           Thu Dec 31 03:38:00 MT 

      env_ file      [mvertens,other]                 ----
      settings
 

3.   Create_production_test completed   [dfeddema,Jan 08 12:32:00 ET ]           
 
            
4.   Debug smoke test completed [dfeddema,Jan 11 14:13:00 ET ]


5.  Performance review completed [who,when]
 