General Information

   Purpose of Run: [short description]

   Scientific Lead: [hurrell, eg]

   Software Engineering Lead: [requestors_name]

   Assigned to: hteng
   Date: 2010-10-29

   Run Length:  [initial estimate]
Case Creation Information (all fields are required)

   CCSM tag:   [tag_name]

   Case Name:  b40.dp.hd-1966.20C.1d.003

   Machine:    jaguarpf

   Compset:    B_1850-2000_CN
   Resolution: 0.9x1.25_gx1v6

Pre-Configuration Information

   Runtype: [startup,hybrid,branch]   
   [if hybrid, specify RUN_STARTDATE, RUN_REFCASE, and RUN_REFDATE]
   [if branch, specify                RUN_REFCASE, and RUN_REFDATE]

   env_conf.xml mods 

   * [place any env_conf.xml mods here] [note: replace "<" with <   and ">" with > for proper html display]

   env_mach_pes.xml mods
  * [place any env_mach_pes.xml mods here] [note: replace "<" with <   and ">" with > for proper html display]

Post-Configuration Information


  * [put any special Buildconf directory changes here]

SourceMods Information

  * [put any special SourceMods instructions here]

Performance/Cost Estimates

  * [put estimated cost/performance info here]
Special Instructions

  * [put any special instructions here]

Pre-Run Instructions

  * Run create_production_test
  * Run debug smoke test

  * Add NCAR Software Levels info to checklist 

Run Instructions

  Run Length: [run_length years] 

  Account key:  [required for bluefire and any other machine with more than one account]

  Priority/Targeted queue:  [eg, premium]


Diagnostics Plan

  * [put diagnostics plan here]

Additional Information

  * [put any additional information here]

Return to Top

Run Checklist

Complete the following checklist prior to beginning the production run:

1.  Update status file: /web/web-data/cseg/ccsm4_0_runs/b40.dp.hd-1966.20C.1d.003/status.html:

2.  Document NCAR software levels at beginning of run (use the spinfo command on bluefire)

3.  Complete the following table, as necessary, showing
    the component liaison's name and the date the setup
    was approved.

   Component         Liaison/                     Date Approved

      atm            [hannay,eaton,other]             ----

      cpl            [kauff,mvertens,tcraig,other]    ----

      ice                 dbailey                     ----

      lnd            [erik,slevis]                    ----

      ocn            [njn01,bates,gokhan]             ----

      env_ file      [mvertens,other]                 ----

      data           [strand,other]                   ----

4.  Create_production_test completed   [who,when] 

5.  Debug smoke test completed [who,when]

6.  Performance review completed [who,when]

Return to Top